Search

Station 6 updates


To receive updates on the project:

Text GJFD6 to 888777
Or visit us on social media:  
GJFD twitter link


Update Weeks of August 10th-23rd:

Street improvements continue along 27 Road this week and next with some lane closures and traffic slowing expected. At the station, brickwork and roofing continue to progress nicely and interior drywall work will begin next week.

August 10th-6th

  • Street improvements continue along 27 Road, some delays expected
  • Exterior brickwork and siding continues
  • Exterior insulation installed

August 17th-23rd

  • Street improvements continue along 27 Road, some delays expected
  • Roof work begins
  • Exterior brickwork and siding continues
  • Interior drywall work begins
  • Slab preparation for apparatus bays

August 24th-30th

  • Exterior concrete work begins
  • Drywall work continues
  • Bay and tower roof work begins
  • Concrete slab poured in apparatus bays

 

August 31st-September 6th

 

  • Exterior concrete work continues
  • Interior painting begins
  • Utility work begins in the bay

For Questions or Concerns:

Matt Carson 
Battalion Chief
(970)549-5871
mattc@gjcity.org


August 12th

July 27th


July 21st

July 7th

June 30th

June 24th


June 9th