[ARCHIVED] Projects Affecting Traffic for the Week of April 3, 2023

Public Works Projects Graphic

City of Grand Junction Projects with Travel Restrictions

2022 Waterline Replacement – Phase 1 Project

Waterline construction is ongoing

  •  Kennedy Avenue between 19th Street and 22nd Street
  •  20th Street between Glenwood Avenue and Kennedy Avenue
  •  21st Street between North Avenue and Kennedy Avenue

 Expect temporary road closures with well-marked detour routes in place.  Access for residents and businesses will be maintained. Anticipated Completion – April 2023

 24 Road and G Road – Traffic Roundabout Project

  • Be aware of the posted 15 mph speed limit around the 24 Rd. and G Rd. temporary roundabout 
  • Continue to see lane shifts on 24 Rd. from I-70 to Leland Ave.
  • Moderate traffic delays can be expected
  • Access to Canyon View Park, Golden Gate Petroleum & Community Hospital will be maintained

Sewer Replacement Project- (Orchard Mesa)

  • Cedar St. north of Unaweep Ave. will be closed between the hours of 8 am and 4pm
  • Resident access will be provided
  • Anticipated Completion – Mid April

Mesa Avenue Waterline Upgrade Project 

  • Mesa Avenue east of 28 Road is closed to thru traffic
  • Resident access will be provided
  • Anticipated completion – Early April

 2022 Safe Routes to School Project – Asphalt Patching

  • Elm Ave. is closed to thru traffic from Eastgate Ct. to 28 ¼ Rd.
  • Resident access will be provided
  • Anticipated completion – Wed. April 5

Non-City of Grand Junction Projects with Travel Restrictions

Fiber optic construction– Highline Internet Service Provider

Expect Lane Shifts and possible delays this week at the following locations:

  • Westbound Patterson Rd. from Broken Spoke Rd. to 29 ½ Rd.
  • Northbound 29 ½ Rd. from Patterson Rd. to F ½ Rd.
  • 28 Rd. from Orchard Ave. to Texas Ave.
  • 28 ¼ Rd. from Hall Ave. to Texas Ave.                   

 12 Road (Loma) from M Road to M ½ Road, Utility Construction – Ute Water

  • 12 Road is closed south of Hwy 6&50 between M Road and M ½ Road 
  • Detour route will be in place
  • Anticipated Completion – Early April

 Railroad Crossing Replacement– Union Pacific Railroad

Starting April 4, four railroad crossings will be closed one at a time in the following order. Each will take approximately four days to complete

  • 31 ½ Rd.
  • 32 ½ Rd. 
  • 33 Rd.
  • 33 ¾ Rd.

Anticipated completion date: April 11 - weather dependent

 