News Flash Home
The original item was published from 1/19/2023 4:08:51 PM to 1/27/2023 3:05:00 PM.

News Flash

City of Grand Junction News

Posted on: January 20, 2023

[ARCHIVED] Projects Affecting Traffic for the Week of January 22, 2023

Public Works Projects Graphic

City of Grand Junction Projects with Travel Restrictions

2022 Waterline Replacement – Phase 1 Project

  • Construction will be taking place at the following locations and in the order shown below (subject to change)
  1. Hall Avenue between 15th Street and 18th Street. The waterline is complete and the final asphalt paving will be done in spring 2023.
  2. 17th Street between Glenwood Avenue and Hall Avenue
  3. 16th Street between Texas Avenue and Hall Avenue. The waterline is complete and the final asphalt paving will be done in spring 2023. 
  4. Texas Avenue between 15th Street and 17th Street. The waterline is complete and the final asphalt paving will be done in spring 2023. 
  5. 18th Street between Glenwood Avenue and Elm Avenue
  6. 19th Street between Glenwood Avenue and Elm Avenue
  7. Kennedy Avenue between 19th Street and 22nd Street
  8. 20th Street between Glenwood Avenue and Kennedy Avenue
  9. 21st Street between North Avenue and Kennedy Avenue
  • Expect temporary road closures with well-marked detour routes in place
  • Access for residents and businesses will be maintained
  • Anticipated Completion – April 2023

Non-City of Grand Junction Projects with Travel Restrictions

South Broadway Shoulder Widening Project between Rado Drive and Desert Hills Road - Mesa County

  • Hours of operation:  Monday – Friday from 7 a.m. to 5 p.m. 
  • Expect intermittent alternating one-lane traffic during the duration of the project
  • Delays can be expected 
  • Anticipated Completion – Early April 2023
  • For more information please contact the Project Hotline at: (970) 609- 9681


30 Road area, Fiber installation – Highline Internet Service Provider

  1. Alternating one-lane traffic on 30 Road between Patterson Road and F ½ Road
  2. Patterson Road westbound lane shift between 30 ½ Road and 30 Road
  • Work hours will be 8 a.m. to 4 p.m. daily
  • Expect delays
  • Anticipated Completion – Friday, January 27, 2023.