City of Grand Junction Projects with Travel Restrictions
NOTHING TO REPORT THIS WEEK
Non-City of Grand Junction Projects with Travel Restrictions
1st Street Between North Avenue and Grand Avenue, Gas Line Replacement Project – Xcel Energy
- 1st Street will be closed at night from North Avenue to Grand Avenue, between the hours of 8:00 p.m. and 5:30 a.m.
- A detour route will be in place
- 1st Street will remain open every day between 6:00 a.m. and 9:00 p.m. with no delays anticipated
- Anticipated completion - Early May
E Road Reconstruction between 31 Road and 32 Road – Mesa County
- Expect full Road Closures with a well-marked detour route at various locations
- Resident access will be maintained
- Alternate Route advised
- Work hours: Monday thru Saturday, 7:00 a.m. to 7:00 p.m.
- Anticipated Completion: September 2021
Hwy 340 (Broadway) Culvert Improvements – CDOT
- Construction will take place between Canary Ln. and Dressell Dr.
- Expect single-lane closures
- Work hours will be Monday through Saturday from 7:00 a.m. to 7:00 p.m.
G Road Power Pole Renovation Project Between 26 ½ Road and 27 Road – GRAND VALLEY POWER
- Possible alternating one-lane traffic through the work zone
- Expect delays
- Work hours: Monday through Friday, 8:00 a.m. to 5:00 p.m.
- Anticipated Completion – Late April
12 Road North of Hwy 6 & 50, Utility Construction – Ute Water
- 12 Road is closed to thru traffic
- A detour route will be in place
- The road will open on evenings and weekends
- Anticipated Completion – Early July
O Road between 12 Road and 13 Road, Utility Construction – Ute Water
- O Road is closed to thru traffic
- A detour route will be in place
- The road will open on evenings and weekends
- Anticipated Completion – Early July